black

专业英语

登录

单项选择题

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

A.Benefitcontribution
B.Expertjudgment
C.Scoringmodels
D.Flowcharting

相关考题

单项选择题 Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

单项选择题 Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

单项选择题 Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

All Rights Reserved 版权所有©PP题库网库(pptiku.com)

备案号:湘ICP备14005140号-5

经营许可证号:湘B2-20140064