单项选择题

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved ()that can serve as a baseline to track progress.

A.scope statement
B.Activity list
C.project charter
D.Project schedule

相关考题

单项选择题 ()is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.

单项选择题 The project life-cycle can be described as()

单项选择题 Risk management allows the project manager and the project team not to()