单项选择题
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
相关考题
-
单项选择题
Contract closeout is a process that involves()
A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout -
单项选择题
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix -
单项选择题
You are working on the cost budget for one project. Which of the following is true()
A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.