An administrator is planning a cluster running applications in 3 separate resource groups.
RGA - Database 1
RGB - Web Server
RGC - Database 2
Database 1 and Database 2 must be online before the Web Server. All resource groups have a Startup Policyof Online on Home Node Only.
Which of the following will ensure that the resource groups are processed in the correct order?()

    A.Set the Serial Acquisition Order
    B.Set the Parallel Acquisition Order
    C.Configure Online on the Same Node Dependency
    D.Configure Online on Different Nodes Dependency