欢迎来到PP题库网 PP题库官网
logo
全部科目 > 计算机软件水平考试 > 信息系统项目管理师 > 高级信息系统项目管理师 > 专业英语

单项选择题

共用题干题

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(3)处填()

    A.F-S
    B.F-F
    C.S-F
    D.S-S

点击查看答案&解析

相关考题

微信小程序免费搜题
微信扫一扫,加福利官免费搜题

微信扫一扫,加福利官免费搜题