The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
A.Evaluate phase exit milestones using sufficiency criteria
B.Flexible entry and exit criteria to minimize schedule delays
C.Quality measures reported only to the project steering committee
D.Many work teams with few members to maximize the number of deliverable hand-offs
相关考题
-
单项选择题
Iftheorganizationalspendingplanhasallocated$100,000foraproject,andthehighlevelbudgetestimateforthatprojectis$200,000;whichofthefollowingisaccurate?()
A.The high level budget estimates are inaccurate
B.The organizational spending plan is inaccurate
C.The budget is not aligned with the spending plan of the organization
D.The detailed bottom up budget will need to be adjusted -
单项选择题
Whatistheroleofthelinemanagerinaprojectplan?()
A.Provide resources to a project
B.Request requirements changes
C.Resolve team conflicts
D.Control the project budget -
单项选择题
Teammemberlisting,scheduledtasks,andriskidentificationarepartofthe:()
A.project plan.
B.project charter.
C.communication plan.
D.WBS (Work Breakdown Structure).