An application running on a production cluster failed over to the backup node, however, the DLPARintegration scripts failed.

On inspection, it was discovered that the scripts failed as a result of /var being 100% full. The administratoradded more space to /var and ran the following command:
Which of the following is the correct next action?()

    A.Refresh the RMC daemon using rmcctrl
    B.Refresh the RSCT subsystem using SRC
    C.Recover from script failure using clruncmd
    D.Reconfigure the RSCT subsystem using recfgct