An insurance customer installs two BladeCenter chassis in a rack with glass doors. After a short time, the blowers in both BladeCenters increase to full speed, and then one fails. Apart from replacing the broken blower, which additional action is required for a long term fix? ()

    A.Add Rear Door Heat eXchanger 
    B.Add fans to the top of the racks 
    C.Increase circulation from Data Center raised floor 
    D.Change to perforated doors