Who is responsible for authorizing closure of the project?()
A.Project Manager
B.Stakeholder
C.Customer
D.Executive Sponsor
点击查看答案
相关考题
-
单项选择题
Acceptanceofdeliverablestomultiplelocationsrequireswhichtypeofsignoff?()
A.Design Acceptance
B.Code Acceptance
C.Module Acceptance
D.Site Acceptance -
单项选择题
ThelastdeliverableattheCloseOutmeetingis:()
A.source code.
B.passwords.
C.lessons learned.
D.test results. -
多项选择题
A customer wants to increase the performance of an existing server. They are running a very network intensive application and feel that increasing the bandwidth to the network will fix their problem. They are running two 24-port autosensing 10/100 hubs, tied together with a standard Ethernet crossover cable in port 24. The server is running IPX. After adding a second network card and plugging one card into each hub, they have not seen any performance improvement. Which two are likely reasons why implementing network adapter teaming has not improved performance?()
A. Adapter teaming is designed to work with switches.
B. Adapter teaming only functions with gigabit network cards.
C. Adapter teaming only provides fault tolerance, not additional bandwidth.
D. Adapter teaming only works with IPX when using switches and network cards with special features that support teaming.