单项选择题
A customer has a requirement for a server to run Windows Server 2003 Enterprise Edition and Exchange 2003 Enterprise Edition. It has been determined that 4GB RAM will be needed. The customer is trying to decide between the two following configurations:
(1)An IBM xSeries x366 with 4 Xeon MP processors and 4 x 1GB memory DIMMs.
(2)An IBM xSeries x445 with 4 Xeon MP processors and 8 x 1GB memory DIMMs.
Which question should be asked to guide the customer in selecting the correct memory configuration?()
A.Is rack space an issue?
B.Is there a high cache-hit ratio?
C.Is this a mission-critical application?
D.Are there plans to expand the memory to 8GB in the future?
相关考题
-
单项选择题
AcompanywantsasolutiontoconsolidatetheirstorageusingtheDS4000seriesandimplementadisasterrecoverysolutionacrosstwodatacenterslinkedbyfibretoduplicatetheproductionenvironment.Thecustomerrequiresasolutionwiththeleastamountofsystemadministration.Whichconfigurationwouldprovidethebestsolution?()
A.Implement one DS4400 at each location connected to the fibre link and use Remote Volume Mirror (RVM).
B.Implement a DS4400 at each location using FlashCopy option and use host based replication to synchronize the sites.
C.Implement a switched fabric using redundant SAN switches with a DS4300 using RVM option at each location.
D.Implement a switched fabric using SAN switches connected via ISL with a DS4300 using RVM option at each location. -
单项选择题
A customer has a need for an xSeries server for an application requiring 12GB memory with the capacity of up to 20GB. The HDD configuration needs to be as follows: (1)Two drives RAID-1 for the operating system (2)Five drives for Data in a RAID-5 configuration with one Hot-Spare (3)All drives have to be internal. Which of the following will satisfy the requirements for the application?()
A.x366
B.x255
C.x346
D.x455 -
单项选择题
AcustomerpurchasedanewIBMxSeriesx445.Theyalreadyhaveanon-IBMindustrystandardrackwith14Uofopenspacethatisbeingconsideredtohousethenewserver.TherackhousesanexistingUPSunitfortheentirerack.Whichofthefollowingquestionsismostimportanttoensurethatthepowerinthedatacenterenvironmentisreadyfortheinitialinstall?()
A.Have optional Fibre Channel and Ethernet switches been installed in the server?
B.What is the available kVA value of the UPS?
C.Are there sufficient empty socket outlets in the UPS?
D.What is the impact on the power consumption of the data center cooling system?