单项选择题
A customer has several small AIX applications that are expected to grow over the next several years. The biggest challenge facing the customer is determining the growth rate of the applications and the I/T requirements needed to support the growth. They are also concerned about the under-utilization of their IT resources. What should the pSeries technical specialist recommend to address this challenge?()
A、Install a p615 per application.
B、Install a p650 with AIX 5.2 and dynamic LPAR and CUoD.
C、Install the appropriate solution once the requirements are understood.
D、Install a POWER5 system with AIX 5.3, Advanced POWER Virtualization, and CoD.
相关考题
-
单项选择题
A customer has asked for a p690 system with the following requirements: ? 32 1.9ghz processors ? 128GB of memory ? 20 fiber adapters ? 7 network cards ? 10 LPARs What is the most appropriate question to ask them in order to build the hardware configuration correctly?()
A.What version of AIX is needed?
B.Which SWMA offering is needed?
C.What kind of network is the system being attached to?
D.What kind of memory should be configured on the system? -
单项选择题
Acustomerisorderinganewp650servertobeplacedintoanexistingOEM42U19-inchrackcontainingonlytwop630servers.Thisisthefirstp650intheenterprise.Whatisthemostimportant questionthatthepSeriestechnicalspecialistshouldaskthecustomerbeforetheorderisplaced?()
A.Have the PDU requirements been met?
B.Are there sufficient KVM connections?
C.Is there sufficient service clearance?
D.Is there sufficient space in the existing rack? -
单项选择题
ApSeriestechnicalspecialistisconfiguringthenetworkadaptersforanHACMPcluster.Theplanistouseafour-portEthernetadapterwithIPATviaIPaliasingforthetwoserviceIPlabels.Whichofthefollowingwouldbeacriticalconcernwiththeproposedconfiguration?()
A.A four-port adapter is not supported.
B.The four-port adapter is a single point of failure.
C.There should be a spare port for each service IP label.
D.The four-port adapter could be a potential performance bottleneck.